House Rehab – East English Village, Detroit

I bought a house in Detroit’s East English Village neighborhood this past April and have been rehabbing it over the last several months. The house was a foreclosure and had probably been vacant for just a year or so, but long enough that the garage door, water heater, and even all the door knobs from inside had been taken and scrapped. I even had some visitors while I was going through the closing process who stopped by to eat a bunch of pizza rolls and other microwaveable food, and I assume also sleep on the floor.

I wouldn’t call it done, because it probably never will be, but it’s close enough now that I can share some before and after photos.

house - before

I had a functional side door, but one of the first things I did was to put the front door back on and replace the locks. I also had a contractor put on a new roof, re-plumb the entire house, update the electrical, rebuild the furnace, and install a new water heater.

house - without door house - with door
house - new roof

Garage:
garage - before garage - after

Living Room:
living room 1 - before

living room 2 - before

living room 3 - before

Downstairs Bathroom:
downstairs bathroom - before downstairs bathroom - after

Side Room:sun room - before

side room - organ

Dining Room:
dining room - before

dining room - bar

Kitchen:
kitchen 1 - before
kitchen 2 - before

kitchen - breakfast nook

Stairs/Hallway:stairs - before

Midway through the progress…
stairs - progress
hallway - before hallway after

hardwood floors

stairs - middle

Removing Boarded Windows:

Shoutout to my friend and now neighbor, Eric, who through this process: lent me a lawnmower, let me use the bathroom in his house while I was working on mine and had no running water, lent me tools (including a heat gun that I haven’t actually given him back yet), let me crash in his guest room longer than expected after my lease was up and house was still not ready, helped move furniture, and can be seen here taking a board off a window:  removing boarded windows - eric
removing boarded windows

Back Bedroom:back bedroom - beforeback bedroom - after

Upstairs Bathroom:upstairs bathroom - beforeupstairs bathroom - after

Front Bedroom:front bedroom 1 - before

front bedroom 2 - before front bedroom 2 - after

front bedroom 3 - before

 

Standard

3 thoughts on “House Rehab – East English Village, Detroit

  1. GREAT JOB! i am writing a report for the city and for the east side neighborhoods and one chapter is about the vacant housing. would you give me permission to use your before photo? the report discusses how the vacant houses in this area are in relatively good condition and your photo is a great illustration of that. thanks!

Leave a comment